November 16, 2018

  • Request for Proposals (RFP) published on www.liveunitedm-i.org
  • Email notice will be sent to all current United Way Funded Partners

December 7, 2018

  • Grant Applications may be submitted to United Way Montcalm-Ionia Counties

December 4, 2018   (8:30 - 10:30 AM, Tuesday)
or
December 7, 2018   (1:30  - 3:30 PM, Friday)

MANDATORY Q&A Grant Informational Session
(All applicants MUST attend one of the following meetings.)

  • All Informational Sessions will be held at United Way Montcalm-Ionia Counties
    10260 S Sheridan Road, Fenwick, MI 48834
  • Grant applications will only be accepted from organizations that have attended one of these meetings.

December 20, 2018

  • Completed Grant Applications due by 12:00 PM
  • Grants will NOT be accepted if received after 12:00 PM.
  • Grants MUST be physically received in our office on December 20, 2018 on or before 12:00 PM.

January 28, 2019 - February 15, 2019

  • Community Impact Grant Review Process

February 2019

  • Slate of recommending grant awards approved by United Way Montcalm-Ionia Counties' Board of Directors

March 2019

  • Community Impact Grant Funding announced
  • Mandatory check presentations and media opportunities begin.

October 31, 2019

  • Six-month progress report due.

March 31, 2020

  • End-of-year one progress report due.

October 31, 2020

  • Eighteen-month progress report due.

March 31, 2021

  • End-of-year two final report due.